Teams of Orenburgskoye Production office of Orenburgenergo Branch of IDGC of Volga, PJSC (a member of Rosseti) are engaged in the scheduled grids repair works. Capital and current repairs were made on 296 transformer substations, about 1.55 km cable lines and 154.4 km of power transmission overhead lines.
This year the power engineers will repair the power grids on 22 streets of Orenburg and in 44 rural settlements of Orenburgsky district. Safe repairs can be conducted only with temporary power cutoff.
Twenty four hours before commencement of works the power engineers warn the heads of the settlement authorities as well as the management companies and housing cooperatives in charge of the electrical facilities of businesses and organizations on the exact date and time of cutoff and on the list of the streets where will be no power supply.
The relevant announcements are also placed by the company specialists on the information boards of the department stores, post offices and medical and obstetrical stations.
|