Capacities commissioning is equal to 2 MVA and 20 km of transmission lines. Komienergo branch of IDGC of the North-West, JSC has summed up the results of the Investment Program execution in Q1 2012. During the 3 months investments in development of the electric power grid complex of the Republic of Komi made 174 mln RUR (the planned amount having been 25.3 mln RUR). Komienergo branch allocated 25 mln RUR for implementation of projects on facilities included in the plan. Additionally, 148 mln RUR were assigned for execution of contracts for technological connection to the electric power grid. Most of the funds were spent on connection of Yamalgazinvest Company's facilities connection. The amount of fixed assets commissioned in Q1 of the current year within the framework of the Investment Program is 36 mln RUR. Capacities commissioning is equal to 2 MVA and 20 km of transmission lines. All in all, Komienergo branch of IDGC of the North-West, JSC intends to allocate 1 bln 131 mln RUR for implementation of the Investment Program of IDGC of the North-West.
|