On Tuesday, February 27, an expanded meeting of the Governing Board of OAO Mosenergo with the participation of subsidiary directors will be held to discuss the results of OAO Mosenergo’s production and business activities in 2006 and objectives for 2007.
On Wednesday, February 28, a meeting of the field construction headquarters for power-generating units No. 3 and No. 4 will be held at OAO Mosenergo’s TETs-27.
On Friday, March 1, a meeting will be held at OAO Mosenergo on questions of engineering design and equipment deliveries for construction of the new power-generating units at TETs-21 and TETs-27.
The turbine bases in the new main building of power-generating unit No. 3 at TETs-27 are currently nearing completion, and installation of the power boilers and preparation of the pile foundation of power-generation unit No. 4 are continuing. Installation of the main building’s steelwork is continuing at TETs-21. Preparation of the construction site at TETs-26 for transfer to the general contractor, Alstom, is currently being completed.
Construction of new power-generating units and technical reequipment of OAO Mosenergo’s power plants are based on the latest steam-gas cycle technology, which guarantees an efficiency factor of 52-59% (at plants with steam-power units, the efficiency factor is no more than 38%). The highly efficient steam-gas units allow gas savings of up to 25%, while reducing harmful atmospheric emissions by one-third. Commissioning of the first PGU-450 steam-gas power-generating unit at TETs-27 will take place in the fourth quarter of 2007.
|