The cost of the project will make approximately 5.5 mln RUR. The cost of the project for construction of “Airport Neighborhood” 10/0.4 kV overhead line in the Imeni Babushkina Village, Vologda Region (which project the grid company intends to complete by the end of 2012) will make approximately 5.5 mln RUR. Construction of a 10-0.4 kV overhead line (involving usage of self-supporting insulated cables) and five 10/0.4 kV package transformer substations is to be carried out at the power industry facility. Currently, the route setting out and installation of 50 poles have been carried out at the site by the contractor’s efforts.
|