The power industry company’s CAPEX on implementation of the socially significant investment project have made approximately 5.5 mln RUR.
Vologdaenergo branch of IDGC of the North-West has put in operation new “Mikrorayon Aeroport” 10/0.4 kV overhead transmission line newly constructed in the Imeni Babushkina Village (Vologda Region). The power industry company’s CAPEX on implementation of the socially significant investment project have made approximately 5.5 mln RUR. Within the framework of the works one has constructed within the facility a 10-0.4 kV overhead transmission line of self-bearing insulated wires and has installed five 10/0.4 kV package transformer substations.
|