The facility is located within the territory of the former stone-processing factory IDGC of the North-West (branch company of Russian Grids, JSC) has performed design works for technical re-equipment of Substation No. 20 “KOZ”, involving replacement of the 10 MVA transformer with a 16 MVA one. The facility is located within the territory of the former stone-processing factory. The project implementation, planned for 2013–2014, will enable increase of the facility capacity from 20 MVA to 26 MVA and connection of additional loads for consumers in the city of Kondopoga.
|