July 7, 2011

At the substation 110/35/10 kV "Antushevo" in the Vologda region is completed the installation of gas (SF6) circuit breakers

To complete reconstruction of the substation, "Vologdaenergo" plans by the end of 2011.

During the reconstruction of the substation 110/35/10 kV "Antushevo", located in Belozersky District (Vologda region), "Vologdaenergo" performed (by the contractor) construction works at the site and began assembling of electric equipment.

At the substation "Antushevo" were  installed five gas-insulated breakers 35 kV and 12 disconnectors in outdoor switchgear 35 kV. In addition, in outdoor switchgear 110 kV being installed 3  gas-insulated circuit breakers and 8 disconnectors. By the end of July at a power plant is also planned to install new power transformers 6.3 MVA.

The project realization will allow to improve the reliability of electricity supply to consumers of Vologda region, as well as allow the accession of additional capacities.
To complete reconstruction of the substation, "Vologdaenergo" plans by the end of 2011. Capital investment in the project will be about 199 million rubles.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer