Komienergo plans to spend about 800 thousand rubles for this project. In 2011, "Komienergo" will repair 18 km of transmission line 110 kV Sosnogorsk CHP - substation 110/35/6 kV "Pashnya". These measures will improve the reliability and quality of electricity supply. As part of the repair program, in June 2011 were replaced 10 wooden "Ï-shaped" poles. During the operations the electricity supply to the consumers not been broken, it was carried out by a backup circuit. Also before the end of 2011 will be mounted 205 vibration damper. The operations were caused by wear and tear of poles on this part of transmission lines having a total length of 121 km. The line was commissioned in 1965 Komienergo plans to spend about 800 thousand rubles for this project.
|