Capital investments will be about 228 million rubles.
In the frames of the reconstruction of the substation 110/10 "Iskra" in Cherepovets (Vologda region), a branch of JSC "IDGC North-West" "Vologdaenergo" assembled and installed two new power transformers TOTRc with capacity 40 MVA each. In addition, during the reconstruction is fully completed the installation of outdoor switchgear 110 kV.
Currently, at the substation are conducted assembling operations in a building of control center and in the indoor distribution system . It is planned to finish the operations in the beginning of August 2011.
Substation "Iskra" is one of the priority projects of the investment program 2011 of "Vologdaenergo." . In general, the reconstruction of the substation is provided in accordance with the approved schedule. Capital investments will be about 228 million rubles.
|