The amount of CAPEX assigned by the power industry company for the socially significant project made 169.4 mln RUB.
Vologdaenergo branch of IDGC of the North-West, JSC has commissioned “Roslyatino” 110/10 kV substation in the Babushkinsky District, Vologda Region after reconstruction. The amount of CAPEX assigned by the power industry company for the socially significant project made 169.4 mln RUB. The project implementation has enabled the grid company to ensure reliable and uninterrupted power supply to the socially significant facilities energized from “Roslyatino” 110/10 kV substation.
|