Following the outcome of Q1, 26.01 ÌVÀof transformer capacities and 320.69 km of 0.4–150 kV transmission lines were commissioned. IDGC of the North-West, JSC has summed up the results of the Investment Program implementation in Q1 2013 that were announced at the session of the Management Board of the Company. During the period referred to, CAPEX on development of the electric power grid complex made 789.032 mln RUR (as compared to 574 mln RUR in the same period of the previous year). Following the outcome of Q1, 26.01 ÌVÀof transformer capacities and 320.69 km of 0.4–150 kV transmission lines were commissioned. The volume of fixed assets commissioning made 673.326 mln RUR. The sum total of works funding was 977.486 mln RUR. For reference: within the framework of 2013 Investment Program, IDGC of the North-West, JSC plans to invest 6,497.805 mln RUR in the electric power grid complex development.
|