Orenburgproduction division of the Rosseti Volga branch (brand of IDGC of Volga, PJSC) - Orenburgenergo has fulfilled most of the planned program for the eight months of the repair campaign. Capital and current repairs of 661 transformer substations, more than 356.5 km of power transmission lines of 0,4/6/10 kV were carried out.
Power engineers replaced 108 wooden poles with reinforced concrete ones, about 10 km of bare wire with insulated one. To maintain the reliability of operation of OPL, employees of RES cleared the protective zones from tree and shrub vegetation. Repairs of power grids have been completed on 9 streets. Safe performance of works on power lines is impossible without short-term power outages. About all temporary breaks of power supply the employees of the power grid company warn in advance housing and communal organizations, place information on the website of administration of Orenburg, city portals.
Residents of Orenburg can also learn about planned power outages by calling the dispatching service of the Orenburg production division. Power engineers will complete repairs by the beginning of October, and will receive the passport of readiness for work in the autumn-winter period after checks of the Commission.
|