December 14, 2020

The "Orenburgenergo" branch completes the implementation of the investment program in 2020

The branch of PJSC "Rosseti Volga" - "Orenburgenergo" is completing the construction, reconstruction and technical re-equipment of power grid facilities, provided for by the investment program of 2020.

For 11 months, the power engineers carried out work on 1191 objects. The length of the introduced power transmission lines exceeds 288 km, the volume of added transformer capacity is 14 MVA.

According to the specialists of Orenburgenergo, almost 65% of the total volume of the investment program falls on the work on the fulfillment of the terms of contracts for technological connection and connection of new consumers.

Among the largest projects are the construction of electric networks to provide backup power to broadcasting facilities, the reconstruction of substations to connect solar power plants in the Svetlinsky district.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z



Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer