Power engineers of Mordovenergo, a branch of IDGC of Volga, JSC (a member of Rosseti Group of Companies) continue their activities to implement the Repair Program. According to the schedule, the company will repair 5 substations this month: B.Ignatovo 110/35/10 kV Substation, B.Berezniki 110/35/10 kV Substation, Kochelaevo 110/10 kV Substation, Khadzhi 35/10 kV Substation and Krasnaya Rudnya 35/10 kV Substation. 5 transformer substations (10/0.4 kV) and 12 power transformers (10/0.4 kV) have been already repaired. 88 km of 35-110 kV overhead transmission lines will be also repaired. The central repair office of Mordovenergo reports that in June its employees will replace 3 bare wire leads of 10 kV overhead transmission lines with armored wire at electrical substations.
|