print version 

Find company
Home About the ProjectContact usFor the Clients
Enter code or ISIN
 
alpha / industry search

Issuers' Corner
Press Releases
Annual Reports Library

Financial Statements
SEC & FFMS Filings
Corporate Presentations
GM Materials
Issues Documents
Corporate Governance Materials
Russian Company Guide
Company Profiles
Corporate Calendar
Markets Corner
Consensus Estimates
Media Corner
News Line


Get updates



Home  Issuers' Corner  Press Releases  Rosseti Volga REGISTER LOG IN

Press Releases > Rosseti Volga  all about the company

company search
all press releases
all Rosseti Volga press releases

Rosseti Volga

July 22, 2019

Technical maintenance and repair program will be implemented in Penzaenergo

Specialists of the ROSSETI Volga branch (brand of IDGC of Volga PJSC) - Penzaenergo are working on the implementation of the technical maintenance and repair program, which is aimed at preparing the power grid complex for the autumn-winter period.

 In accordance with the approved plan of repairs for 2019 overhaul of 34 110 kV substations and 20 35 kV substations and 446 transformer substations has been carried out for the 6 months, 431.3 km of 35-110 kV OPL and 2486.8 km of 0.4-10 kV OPL was renovated.

 The largest facilities of the repair campaign for 2019 were 110 kV Vodozabor substation and 110 kV Klyuchiki-Evlashevo OPL.

 In addition, in the present moment, clearing of 487.2 hectares of glades of OPL-6-110 kV was made.

The greatest amount of clearance with the use of specialized equipment moliterno was made on 110 kV Pachelma-Vadinsk OPL, 110 kV Gorodishche Sosnovoborsk OPL, 110 Kuznetsk Klyuchiki OPL I-II with approaches (110 kV Kuznetsk traction-Evlashevo OPL, 110 kV Kuznetsk-KTM OPL, 110 kV Kuznetsk-Kurmaevka traction OPL), 110 kV overhead line Sursk-Gorodishche OPL, 110 kV Kuznetsk Annenkovo OPL with supply on Druzhba substation, 35 kV Tyunyar-Verkhniy Shkaft OPL, 35 kV Sosnovoborsk-Markino OPL. In accordance with the approved long-term program for 2019, power engineers will clear 987 hectares by October 1.

Conduct of repair works is aimed at ensuring reliable and uninterrupted power supply to consumers of Penza Region.

 

 

 

Search by industry

Agriculture, Foresty and Fishing | Chemicals | Engineering | Ferrous Metals | Financial, Insurance & Real Estate | Food & Kindred Products | General Construction | Information Technology | Media & Publishing | Non-Ferrous Metals | Oil & Gas | Pharmaceuticals | Power Industry | Precious Metals and Diamonds | Telecommunications | Transportation | Wholesale & Retail Trade

Search by alpha index

A B C D F G H I K L M N O P R S T U V W X Z


Site Map
© RUSTOCKS.com
Privacy Statement | Disclaimer