Mordovenergo Branch of PJSC IDGC of Volga, Member of Rosseti Group, has continued work on building the production and technology unit of Drakino 110/10 kV substation in Kovylkinsky District of the Republic of Mordovia.
This work is being carried out in the first quarter of this year as part of the Branch’s investment program. The work is being done as part of the technological connectionconnection state contract. Under the contract, the company will build a 2x10 MVA substation, and two branch lines from the 110 kV AL to the new Drakino 110/10 kV substation, with the total length of more than 22 km.
Reconstruction of 0.4 kV distribution grids, replacement of telemechanics and technological communication equipment will be carried out in the first quarter of 2018 according to the plan of events for this year. Work is currently underway to select contractor organizations. Additionally, technological connection contract work will continue in the 1st quarter as well.
|