In the 2nd quarter of this year, under the investment program of the branch of IDGC of Volga, PJSC (included in the Rosseti group) - Mordovenergo, it is planned to carry out capital measures to fulfill the obligations of the grid organization under utility connection agreements.
It include - the reconstruction of power production and technological complex of the Bolshaya Yelkhovka 110/10 kV substation (SS), as well as the installation of two 10 kV cells at the GKS 110 kV substation for the power supply of the meat processing complex in the Torbeyevsky district. Also, the power engineers will continue the construction of 0.38-10 kV cable lines for the power supply of the secondary school for 450 pupils in the city of Krasnoslobodsk and the power lines for the television repeaters located in the regions of the republic.
It is planned to complete the tender procedures for selecting contractors for the implementation of investment projects planned for 2019 in the 2nd quarter.
By the end of the year, the work will be carried out on the key facility of the investment program for the reconstruction of the power production and technological complex of the construction of Alekseyevka 110/35/6 kV Substation. Power engineers are also planning to upgrade the dispatcher board in the building of the operational and dispatching service of Kovylkinsky PDZ, replace the protection and automatic control panels of the switch at the Yugo-Zapadnaya 110/6 kV substation, install cabinets with microprocessor terminals and replace the accident recorders.
|